Concrete Bag Yield & Coverage Chart

4 min readBy SizeTheJob

Quick answer: a cubic yard of concrete is 27 cubic feet — that's 45 eighty-pound bags, 60 sixty-pound bags, or 90 forty-pound bags. One cubic yard covers about 81 square feet at 4 inches thick. The tables below are the numbers you actually need to order concrete; for an exact figure on your job, use the concrete slab calculator or the matching concrete calculators.

Bags of concrete per cubic yard

Every bag of dry mix lists a yield — the volume of wet concrete it makes. Divide 27 ft³ by the yield to get bags per cubic yard.

Bag size Yield (wet) Bags per cubic yard
40 lb 0.30 ft³ 90
60 lb 0.45 ft³ 60
80 lb 0.60 ft³ 45

Yields are nominal and vary a little by brand and mix, so treat the bag count as a close estimate and buy a spare bag or two.

Concrete coverage by slab thickness

How far a given amount of concrete spreads depends entirely on thickness. These are the two figures people ask for most — area per cubic yard (for ordering ready-mix) and area per 80-lb bag (for small pours).

Slab thickness Coverage per cubic yard Coverage per 80-lb bag
2 in 162 sq ft 3.6 sq ft
3 in 108 sq ft 2.4 sq ft
4 in 81 sq ft 1.8 sq ft
5 in 64.8 sq ft 1.44 sq ft
6 in 54 sq ft 1.2 sq ft

Concrete for common slab sizes

All at the standard 4-inch thickness. Cubic yards are exact; bag counts include about 10% waste (you can't pause a pour, and the subgrade is never perfectly flat).

Slab size Cubic yards 80-lb bags 60-lb bags
4 × 4 ft 0.20 10 14
6 × 6 ft 0.44 22 30
8 × 8 ft 0.79 40 53
10 × 10 ft 1.23 62 82
10 × 12 ft 1.48 74 98
12 × 12 ft 1.78 88 118
12 × 16 ft 2.37 118 157

Notice how fast the bag counts climb: anything past roughly half a cubic yard (about 23 eighty-pound bags) is cheaper and far easier as ready-mix. Use the concrete slab calculator for other sizes and thicknesses.

Round columns & Sonotube fill

A round column, pier, or cardboard tube form (like a Sonotube) holds π × radius² per foot of height. This is the concrete per foot — multiply by your tube height.

Tube diameter Concrete per foot 80-lb bags per foot
6 in 0.20 ft³ 0.3
8 in 0.35 ft³ 0.6
10 in 0.55 ft³ 0.9
12 in 0.79 ft³ 1.3
14 in 1.07 ft³ 1.8
16 in 1.40 ft³ 2.3
18 in 1.77 ft³ 3.0

So a 12-inch tube 4 feet tall needs about 0.79 × 4 = 3.2 ft³, or roughly 6 eighty-pound bags with waste. The concrete column calculator handles any diameter, height, and quantity.

Quick conversions

  • 1 cubic yard = 27 cubic feet
  • 1 cubic yard of concrete ≈ 4,000 lb (about 2 US tons)
  • Bag yields: 80 lb = 0.60 ft³ · 60 lb = 0.45 ft³ · 40 lb = 0.30 ft³
  • Switch to ready-mix past about 0.5 cubic yard (≈ 23 eighty-pound bags)

How to use this chart

For a slab, find your thickness in the coverage table and divide your area by the coverage figure. For a footing or wall, work out the volume (length × width × depth, in feet) and divide by 27 for cubic yards or by the bag yield for bags — the concrete footing and concrete wall calculators do it for you. Most slabs and footings also sit on a compacted gravel base; size that with the gravel calculator. Whatever you pour, order about 10% extra.

Frequently asked questions

How many bags of concrete are in a cubic yard?+

A cubic yard is 27 cubic feet, so it takes 45 eighty-pound bags (0.6 ft³ each), 60 sixty-pound bags (0.45 ft³), or 90 forty-pound bags (0.3 ft³) to make one cubic yard. Past about half a cubic yard, ready-mix is cheaper than bags.

How much does an 80-lb bag of concrete cover?+

An 80-lb bag yields about 0.6 cubic feet — enough to cover roughly 1.8 square feet at 4 inches thick, 2.4 sq ft at 3 inches, or 1.2 sq ft at 6 inches. A 60-lb bag yields about 0.45 ft³ and a 40-lb bag about 0.3 ft³.

How much area does a cubic yard of concrete cover?+

One cubic yard covers about 81 square feet at 4 inches thick, 65 sq ft at 5 inches, or 54 sq ft at 6 inches. Coverage drops as the slab gets thicker because the same volume spreads less far.

How much does a cubic yard of concrete weigh?+

About 4,000 pounds — roughly 2 US tons — for standard concrete at about 150 lb per cubic foot. That weight is why ready-mix is delivered by the truck and bags are limited to small pours.

When should I use ready-mix instead of bags?+

Switch to ready-mix past about half a cubic yard — roughly 23 eighty-pound bags. Beyond that, mixing by hand is slow and ready-mix delivered by the cubic yard is cheaper per yard, and it's the only practical way to place a continuous pour like a wall or large slab.